Submitted on: 2016-08-08

Update:

53 Avenue bridge work completed early, reopens August 11

 

 

53 Avenue over Whitemud Drive

 

Edmonton, August 10, 2016 - Traffic on Whitemud Drive approaching the 53 Avenue overpass will be restored to three lanes in each direction and the Terwillegar Drive on-ramp to Whitemud Drive westbound will reopen by 6:00 a.m. Thursday, August 11, a day ahead of schedule.

 

Girder installation on the overpass was completed today, and after one more night of lane reductions from 10:00 p.m. Wednesday, August 10 until 6:00 a.m. Thursday, August 11, all three traffic lanes and the Terwillegar on-ramp will be reopened.

 

Construction on 53 Avenue over Whitemud Drive began the last week of March.

The City of Edmonton thanks motorists for their patience during this project.

 